Excavation for pipes, drains, etc. should be at least 9 inches wider than the diameter of the pipe to be laid therein. If the soil in which the excavation is to be made is of a loose and sandy nature that is liable to crumble and slide, a slope, say of 3 inches horizontal to 1 foot vertical, should be allowed on both sides of the trenches. If the latter are of considerable depth, it is sometimes necessary to curb or shore up the sides, in which case an allowance should be made in the estimate for the lumber required. If piles are required, they should be figured at so much per linear foot, driven.

ACTUAL COST OF EXCAVATION

8. In order that an idea may be formed of the actual cost of excavating various kinds of soils, figures based on work actually performed are here given. On this work, for a day of 8 hours, a laborer was paid $2, and a driver with a two-horse team, $4.

As a rule, one laborer can excavate about 7 cubic yards of sandy soil in 8 hours. Thus, at the rate of 25 cents per hour, the cost of excavating this kind of soil is about 28½ cents per cubic yard, provided the material is wasted around the building. To this figure, however, must be added 4 or 5 cents to cover the foreman’s wages, the exact amount depending on the number of men under the foreman. This brings the total cost per cubic yard to about 33 cents.

When the material has to be carted away, the cost is further increased. A team with a driver can haul away about 20 cubic yards of soil in a day if the haul is only about ½ mile. In order to do this, however, an extra wagon must be at hand so that the laborers can be loading one wagon while the team is hauling away the other. Thus, the cost of hauling 1 cubic yard of excavated material ½ mile is 20 cents. The total cost, therefore, of excavating 1 cubic yard of sandy soil and hauling it ½ mile is 33 + 20 = 53 cents.

9. If the soil is compact gravel, the cost of excavating, including the foreman’s time, will be from 34 to 65 cents per cubic yard, depending on its hardness. It costs about the same to haul compact gravel as it does to haul sandy soil.

The exact cost of excavating wet soil cannot be given, as the conditions encountered may vary in each case. In a stated time, a laborer will excavate nearly as much wet material as dry material, but the conditions of sheet piling and pumping out water makes the price uncertain.

Such excavation is usually carried on at a cost of from 75 cents to $1.25 per cubic yard.

In excavating rock, three men—one rockman and two laborers—usually work together. For a day of 8 hours, the rockman receives $3 and each laborer gets $2. Together, therefore, the wages of the three amounts to $7 a day. These men will excavate about 6 cubic yards of rock in 1 day, making the rock excavation cost $1.17 per cubic yard. To this must be added the cost of explosives, which is about 10 cents per cubic yard, and the wear on tools. This latter expense can hardly be estimated, but may also be considered as 10 cents per cubic yard, thus bringing the total cost of rock excavation up to $1.37 per cubic yard for rock wasted at the building.

10. To sum up, excavation in sandy soil wasted around the building costs 33 cents per cubic yard; if hauled ½ mile, it costs 53 cents per cubic yard. If the soil is compact gravel and is wasted around the building, excavation costs from 34 to 65 cents per cubic yard; if hauled ½ mile, from 54 to 85 cents per cubic yard. Wet excavation with no piling or pumping costs about the same as dry; with piling and pumping, it costs from 75 cents to $1.25 per cubic yard. Rock work costs $1.37 per cubic yard if wasted around the building. These figures do not include the contractor’s profit.