Slip Joints.—As with brickwork so in masonry great care must be exercised to prevent the different parts of a building settling unequally. When two portions of a building differing considerably in height come together, it is usual to employ a slip or housed joint instead of bonding the walls into each other. This arrangement allows the heavier work to settle to a greater extent than the low portion without causing any defect in the stones.

Footings.—The footings of stone walls should consist of large stones of even thickness proportionate to their length; if possible they should be the full breadth in one piece. Each course should be well bedded and levelled.

Walling.—There are broadly speaking two classes of stone walling: rubble and ashlar. Rubble walls are built of stones more or less irregular in shape and size and coarsely jointed. Ashlar walls are constructed of carefully worked blocks of regular dimensions and set with fine joints.

Fig. 3.—(¼ in. = 1 ft.)

Random Rubble (fig. 3) is the roughest form of stonework. It is built with irregular pieces of stone usually less than 9 in. thick, loosely packed without much regard to courses, the interstices between the large stones being occupied by small ones, the remaining crevices filled up with mortar. Bond stones or headers should be used frequently in every course. This form of walling is much used in stone districts for boundary walls and is often set dry without mortar. For this work the mason uses no tool but the trowel to lay on the mortar, the scabbling hammer to break off the most repulsive irregularities from the stone, and the plumb-rule to keep his work perpendicular.

Fig. 4.—(¼ in. = 1 ft.)

Coursed Rubble (fig. 4) is levelled up in courses 12 or 18 in. deep, the depth varying in different courses according to the sizes of the stones. The stones are dressed by the workman before he begins building, to obtain a fairly level bed and perpendicular face.

Irregularly Coursed Squared Rubble is a development of uncoursed random rubble, the stones in this case being squared with the hammer and roughly faced up with the axe. The courses jump abruptly from one level to another as the sizes of the blocks demand; the interstices are filled in with small pieces of stone called “snecks.”

For Coursed Squared Rubble the stone is faced in a similar manner and set in courses, the depth of each course being made up of one or more stones.