Line B, Manhattan.
| Material. | Method. | Station: | Date: | Number of days. | Linear Feet. | Rate of progress in feet per day. | Remarks. | ||||||
| From | To | From | To | ||||||||||
| Rock | ⎧ ⎨ ⎩ | Top heading Top lift of bench Bottom lift of bench Bottom lift of bench | 108+35 108+35 108+35 108+15 | 107+87 107+87 108+15 107+87 | July 6, '05 Aug. 3, '05 Aug. 26, '05 Sept 11, '05 | July 27, '05 Aug. 14, '05 Aug. 30, '05 Sept 26, '05 | 21 11 4 15 | ⎫ ⎬ ⎭ | 51 | 48 | 0.94 | ⎧ ⎨ ⎩ | Excavation done in normal air and before advance of shield. |
| Rock | Bottom heading | 107+87 | 107+00 | Oct. 23, '05 | Jan. 17, '06 | 86 | 87 | 1.01 | |||||
| Mixed | Bottom heading | 107+00 | 106+64 | Jan. 17, '06 | Feb. 12, '06 | 26 | 36 | 1.38 | |||||
| Mixed | Rock bench | 106+64 | 106+31 | Feb. 12, '06 | Mar. 1, '06 | 17 | 33 | 1.94 | |||||
| Earth | Poling and breasting | 106+31 | 105+58 | Mar. 1, '06 | Apr. 3, '06 | 33 | 73 | 2.21 | |||||
| Earth | Shutters in contact with face | 105+58 | 99+19 | Apr. 9, '06 | Nov. 1, '06 | 206 | 639 | 3.10 | |||||
| Mixed | Rock bench | 99+19 | 98+44 | Nov. 1. '06 | Dec. 29, '06 | 58 | 75 | 1.30 | |||||
| Mixed | Bottom heading | 98+44 | 97+76 | Dec, 29, '06 | Feb. 12, '07 | 45 | 68 | 1.51 | |||||
| Mixed | Rock cut | 97+66 | 93+84 | Feb. 12, '07 | Aug. 6, '07 | 175 | 392 | 2.24 | |||||
| Rock | Full face | 93+84 | 93+21 | Aug. 6, '07 | Sept 2, '07 | 27 | 63 | 2.33 | |||||
| Rock | Center Heading | 93+21 | 92+30 | Sept 2, '07 | Oct. 12, '07 | 40 | 91 | 2.28 | |||||
| Rock | Bottom heading | 92+30 | 90+99 | Oct. 12, '07 | Dec. 6, '07 | 55 | 131 | 2.38 | |||||
| Mixed | Rock cut | 90+99 | 90+49.6 | Dec. 6, '07 | Jan. 3, '08 | 28 | 49.4 | 1.76 | |||||