Line A, Manhattan.

Material.Method.Station:Date:Number
of days.
Linear
Feet.
Rate of
progress in
feet per day.
Remarks.
FromToFromTo
Rock⎧
⎨
⎩
Top heading
Top lift of bench
Bottom lift of bench
108+43
108+43
108+43
107+74
107+74
107+74
July 20, '05
Aug. 8, '05
Aug. 30, '05
Aug. 3, '05
Aug. 23, '05
Sept 27, '05
14
15
28
⎫
⎬
⎭
5769 1.21⎧
⎨
⎩
Excavation in normal air, and before advance of shield.
Rock⎧
⎨
⎩
Bottom heading
Bottom heading
107+74
107+74
107+21
107+21
Sept 27, '05
Nov. 30, '05
Oct. 23, '05
Dec. 29, '05
26
29
⎫
⎬
⎭
5553 0.96⎧
⎨
⎩
Bottom heading timbered to avoid the possibility of a break.
Mixed Bottom heading107+21106+99Oct. 26, '06Nov. 20, '062522 0.88Bottom heading timbered.
Mixed Rock bench106+99106+34Nov. 20, '06Jan. 13, '075465 1.20
Earth Poling and breasting106+3499+11Jan. 13, '07Apr. 17, '0794723 7.69
Mixed Rock cut99+1193+96Apr. 17, '07Oct. 24, '07190515 2.71
Rock Bottom heading93+9693+58Oct. 24, '07Nov. 14, '072138 1.81
Rock Center heading93+5892+42Nov. 14, '07Dec. 27, '0746116 2.52
Rock Bottom heading92+4291+05Dec. 27, '07Feb. 24, '0859137 2.32
Mixed Rock cut91+0590+57Feb. 24, '08Mar. 20, '0825 48 1.92