Line A, Manhattan.

Material.Method.Station:Date:Number
of days.
Linear
Feet.
Rate of
progress in
feet per day.
Remarks.
FromToFromTo
Rock

Top heading
Top lift of bench
Bottom lift of bench
108+43
108+43
108+43
107+74
107+74
107+74
July 20, '05
Aug. 8, '05
Aug. 30, '05
Aug. 3, '05
Aug. 23, '05
Sept 27, '05
14
15
28


5769 1.21

Excavation in normal air, and before advance of shield.
Rock

Bottom heading
Bottom heading
107+74
107+74
107+21
107+21
Sept 27, '05
Nov. 30, '05
Oct. 23, '05
Dec. 29, '05
26
29


5553 0.96

Bottom heading timbered to avoid the possibility of a break.
Mixed Bottom heading107+21106+99Oct. 26, '06Nov. 20, '062522 0.88Bottom heading timbered.
Mixed Rock bench106+99106+34Nov. 20, '06Jan. 13, '075465 1.20
Earth Poling and breasting106+3499+11Jan. 13, '07Apr. 17, '0794723 7.69
Mixed Rock cut99+1193+96Apr. 17, '07Oct. 24, '07190515 2.71
Rock Bottom heading93+9693+58Oct. 24, '07Nov. 14, '072138 1.81
Rock Center heading93+5892+42Nov. 14, '07Dec. 27, '0746116 2.52
Rock Bottom heading92+4291+05Dec. 27, '07Feb. 24, '0859137 2.32
Mixed Rock cut91+0590+57Feb. 24, '08Mar. 20, '0825 48 1.92