Line D, Long Island.

Material.Method.Station:Date:Number
of days.
Linear
Feet.
Rate of
progress in
feet per day.
Remarks.
FromToFromTo
RockBottom heading68+50.669+77June 2, '06Oct. 24, '06144 126.40.87
Earth and rockBottom heading69+7771+22Oct. 24, '06Jan. 13, '0681 145 1.79
All rockBottom heading71+2372+00Jan. 13, '07Mar. 3, '0749 78 1.59
All rockCenter heading72+0075+73Mar. 3, '07July 10, '07129 373 2.89
Earth and rockGoing out of rock75+7377+63July 10, '07Sept 25, '0777 190 2.47
All earthSoft ground77+6390+38.6Sept 25, '07Mar. 7. '08164 1,275.67.78