COST OF AN ACRE OF NORTON'S VIRGINIA.
| Preparation of soil, etc., | 50 00 |
| 850 plants, first class, to be planted 6×8, $25 per hundred, | 212 50 |
| 450 posts, 10 cents each, | 45 00 |
| 450 stakes, 3 cents each, | 13 50 |
| 600 lbs. No. 12 wire, 16 cents per lb., | 96 00 |
| Cost of erecting trellis, | 50 00 |
| Attendance, labor, etc., during first two years, | 125 00 |
| Interest on capital during first two years, at 6 per cent. per annum, | 70 00 |
| $662 00 |
COST OF AN ACRE OF DELAWARE.
| Cost of preparing ground, | 50 00 |
| 1,200 first-class plants, planted 6×6, | 400 00 |
| 450 posts, 10 cents each, | 45 00 |
| 450 stakes, 3 cents each, | 13 50 |
| 600 lbs. No. 12 wire, 16 cents per lb. | 96 00 |
| Cost of erecting trellis, | 50 00 |
| Cost of cultivation two first years, | 125 00 |
| Interest on capital two years, | 92 00 |
| $871 50 |
COST OF AN ACRE OF CATAWBA.
| Preparing ground, | 50 00 |
| Cost of 1,200 plants, 6×6, | 45 00 |
| 450 posts, 10 cents each, | 45 00 |
| 450 stakes, 3 cents each, | 13 50 |
| 600 lbs. wire, 16 cents per lb., | 96 00 |
| Cost of erecting trellis, | 50 00 |
| Attendance during two years, | 125 00 |
| Interest on capital two years, | 39 00 |
| $463 50 |